8:30 AM Check Saddlebrooke sub
8:30 AM Building Plans
10:00 AM SAddlebrooke Switching
8:00 AM Mt Lemmon W/Dan
9
10
11
12
13
14
15
Mother's Day
8:00 AM Sadlebrooke Sub w/Pat
7:00 AM Check Regulator Availability for Cir 42 w / Mobile on TEP
7:00 AM Saddlebrooke Circuit Switcher test
7:30 AM Mgmt team
8:00 AM Y2k Meeting
16
17
18
19
20
21
22
8:30 AM Westinghouse - Valdez
7:00 AM Meet w/ J. danhof - Aepco radio contract
8:30 AM Aepco to connect 69 bus at Saddlebrooke
7:30 AM NRECA Y2K
RON VAC
23
24
25
26
27
28
29
7:00 AM Work on WAATS & NOVA TRAINING PRESENTATION
8:00 AM y2k Contingency Plan Meeting
7:00 AM W Jim Danhof AEPCO radio Contract
7:30 AM Mgmt Team
Eddie Vac
30
31